South Brunswick, New Jersey
Stop the data center at 4405 Route 1
A data center going up near homes on Route 1 wants a state permit for 12 diesel generators, with no limit on emergency use and no monitoring of what comes out.
Comments to NJDEP are due November 9. Here's how →
Three things to know
Power
Likely uses more electricity than every home in South Brunswick combined, around the clock. Its backup generators alone total about 43 megawatts.
Details and sourcesNoise
Cooling equipment that runs 24/7, plus 12 diesel engines tested during the day. No one has shown whether the noise study measured low-frequency hum.
Details and sourcesAir
When all 12 generators run, the permit allows as much smog-forming NOx per hour as a 600-megawatt coal plant. NOx worsens asthma, and diesel exhaust causes cancer.
Details and sourcesWhat you can do
-
Comment to NJDEP by November 9Comment
Tell the state what you think of the air permit. -
Write your state legislatorsWrite
Senator Zwicker, Assemblywoman Drulis, Assemblyman Freiman. -
Contact the GovernorContact
Her own law could mean more diesel burning. What to say -
Join usReddit Bluesky Email
Updates, meetings, and discussion.
What we're asking for · More ways to help · The facts and sources