Full Planning Board application file
The complete application for 4405 Route 1: site plan set, environmental impact statement, and traffic and stormwater reports.
Every public record we're after for the 4405 Route 1 project, and where each one stands. Before filing an Open Public Records Act (OPRA) request, check here so we don't duplicate each other.
Agencies must respond within 7 business days under the Open Public Records Act (N.J.S.A. 47:1A-1 et seq.). Plain-English guide. Already have records, photos or video? Email them to us. We remove residents' personal details before publishing.
No one has requested these yet. Pick one and file it.
The complete application for 4405 Route 1: site plan set, environmental impact statement, and traffic and stormwater reports.
The Board's written approval, including every condition it attached.
Minutes of every hearing on the application, and any recordings, including recordings of the cable TV broadcasts (channels 26 and 45).
The study that designated the Princeton Nurseries site for redevelopment, the plan itself, and the ordinance the Council adopted in 2024.
Any agreement between the township and the developer, including any payment-in-lieu-of-taxes (PILOT) agreement, if one exists.
Any review, memo or comments the Environmental Commission provided to the Planning Board.
The Mayor has said PSE&G must confirm it can reliably supply the project. Any letter or filing confirming that capacity, as held by the township.
The developer's noise study, plus any reports required by the approval to show the facility meets noise limits.
Key question: Did the study test the low-frequency octave-band limits (31.5 Hz and 63 Hz) in N.J.A.C. 7:29-1.2 at the nearest homes, at the nighttime limits, or only the overall dBA level? Low frequencies travel farther.
The application for the backup generators: number and size of generators, emissions estimates and testing schedule.
Records on the pesticide-contaminated soil (dieldrin and chlordane) and the capped soil berms on the site.
Any water allocation, water supply or sewer approvals for the facility.